IES - Integrated Engineering Services
Attock Petroleum - Fire & Gas Management System

Attock Petroleum - Fire & Gas Management System

Complete Fire & Gas Management System including design, engineering, procurement, installation, and commissioning for Attock Petroleum's storage terminal ensuring compliance with safety standards.

Client
Attock Petroleum Limited (APL)
Location
Pakistan
Year
2021
Industry
Terminal

The Challenge

APL required comprehensive Fire & Gas Management System upgrade to meet OGRA safety requirements and insurance mandates. The project demanded complete coverage of tank farm areas, integration with emergency shutdown systems, and compliance with API and NFPA standards.

Project Snapshot

Client
Attock Petroleum Limited (APL)
Location
Pakistan
Industry
Terminal
Year
2021

Our Solution

IESPK executed complete F&G project: System design per API RP 2001 and NFPA 30; Gas detection covering all tank farm zones; Fire detection with flame and smoke sensors; Integration with ESD systems; Control room upgrades with graphic displays; Complete PAGA system for emergency communication.

Scope of Work

1
F&G system design and engineering
2
Detector procurement and installation
3
Control panel installation
4
ESD integration
5
PAGA system installation
6
Commissioning and certification

Technologies Applied

Fire & Gas DetectionEmergency Shutdown IntegrationPAGA SystemsAPI RP 2001NFPA 30 Compliance

Products Used

Gas DetectorsFlame DetectorsF&G Control PanelsPAGA SystemsESD Interface Modules

The Outcome

Comprehensive fire and gas protection meeting regulatory requirements.
Successful insurance audit and premium reduction.
Integration with emergency shutdown systems.
Improved emergency response capability.
Full compliance with OGRA and insurance requirements.

Key Deliverables

Complete F&G detection system

ESD integration

PAGA system

Compliance documentation

Related Topics

fire gas management systempetroleum terminal safetyF&G detection Pakistantank farm fire protectionAPI RP 2001NFPA 30 complianceemergency shutdown systemPAGA system terminal

Explore Related Solutions

Learn more about the technologies and services used in this project

Have a Similar Challenge?

Let's discuss how we can deliver results for your industrial project